Mann Group were engaged by Multiplex to undertake a highly challenging excavation and piling package, involving the major bulk excavation disposal of VENM, contaminated materials (40,000 t) detailed excavation, backfilling, all civil works, environmental protection and geotechnical engineering that were required to be completed in preparation for building works. Mann Group also provided to the client Design and Construct services for the Piling/Shoring/Anchoring works.

The challenging tasks that were completed successfully were, pilling and bulk excavation some 1.5 meters away from the extremely sensitive scanning machine within the hospital. The client installed vibration monitors during the works and all readings returned with success.

Mann group completed this contract without any impact to the adjacent “operational” hospital, all involved congratulated Mann Group on the prompt and professional services provided.